Week 16 and 17

 Week 16 was a little slow until Saturday.  The interior received one coat of paint.  The deck got started and then on Saturday we had 9 guys working and most of the deck was on.  The closet in one of the bedrooms was framed out.

Week 17 Granite is being installed today and tomorrow.  Thursday the kitchen cabinets arrive (the upper cabinets and the fronts and drawers on the lower cabinets).  The granite looks terrific.  I used Inovarq near Eldon's in Coxen Hole.  The deck floor is on and the little roof goes on tomorrow.